UNDER CONSTRUCTION FOR IMPROVEMENTS

We apologize for not having our doors open, but the improvements will be worth it!

10/12/23
Just a brief video of what the rooms look like before we start the renovation.

Room 1

Room 2

10/23/23
All lumber has been moved out and the divider wall has been removed. We now have one big open space.

empty room - wall removed

11/14/23
Walls have a fresh coat of paint and new carpet has been installed. We are getting closer!

empty room
empty room - new carpet

11/16/23
We have so much progress! The lumber bays were designed by an employee of Boehm-Madisen and he is hard at work installing them with help from a few other dedicated employees.

building bays
bay construction
bay construction

11/20/23
The bays are built! It is looking so good. We just have to add our signage and load them up.

showroom with bays

11/30/23
Signage is up, but we are still working on the lumber. We originally planned on opening on December 4, but we decided to postpone a few days so we can provide a better selection of lumber. We will now open on December 7.
All of our lumber is being surfaced and straight line ripped on one edge. We will have a wider variety of lengths of all of our lumber as well. We hope this makes up for the delay.

lumber bay
lumber bay

12/7/23
We are open for business!

ShowRoom